Typical review time for most residential and commercial projects is ten (10) to fourteen (14) business days; provided all required information is submitted and all contractors have become registered with the City.
For new construction, such as new homes, industrial buildings, commercial buildings, etc., review time is typically ten (10) to fourteen (14) business days; provided all required information is submitted. New construction permits are reviewed by multiple departments, requiring longer review times in some instances.
If a plan review has been rejected, a letter will be sent to the applicant requesting further information. Once the required information is received, a re-review of the permit will be performed within the above time frames, depending on project type.